A Gantt chart is a bar chart that illustrates a project schedule used in project management. It was designed and popularized by Henry Gantt c. 1910 to 1915. Modern Gantt charts also show the dependency relationships between activities and the current schedule status. [1]
TaskLoco Starter PacksInstant Loco Expert in 30 secondsPick a pack and get 10 sticky notes that show you everything TaskLoco can do.Pick your Starter Pack free →A Gantt chart is a type of bar chart that illustrates a project schedule. The chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis. The width of the horizontal bars shows the duration of each activity. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements constitute the work breakdown structure of the project. [1]
Modern Gantt charts also show the dependency, or precedence network, relationships between activities. Gantt charts can show current schedule status using percent-complete shadings and a vertical "TODAY" line. Gantt charts are sometimes equated with bar charts. [1]
Gantt charts are usually created initially using an early start time approach, where each task is scheduled to start immediately when its prerequisites are complete. This method maximizes the float time available for all tasks. [1]
Gantt charts are widely used in project planning in the present day. The first known tool of this type was developed in 1896 by Karol Adamiecki, who called it a harmonogram. Adamiecki published his chart only in Russian and Polish, which limited both its adoption and recognition of his authorship. [1]
In 1912, Hermann Schürch published what could be considered Gantt charts while discussing a construction project. Unlike later Gantt charts, Schürch's charts did not display interdependencies, leaving them to be inferred by the reader. These were also static representations of a planned schedule. [1]
The chart is named after Henry Gantt (1861 to 1919), who designed his chart around the years 1910 to 1915. Gantt originally created his tool for systematic, routine operations. He designed it to measure productivity levels of employees and to gauge which employees were under- or over-performing. Gantt also frequently included graphics and other visual indicators in his charts to track performance. [1]
One of the first major applications of Gantt charts was by the United States during World War I, at the instigation of General William Crozier. The earliest Gantt charts were drawn on paper and had to be redrawn entirely to adjust to schedule changes. Gantt's collaborator Walter Polakov introduced Gantt charts to the Soviet Union in 1929. [1]
In the 1980s, personal computers allowed widespread creation of complex Gantt charts. With the advent of the Internet, Gantt charts became a common feature of web-based applications at the end of the 1990s. By 2012, almost all Gantt charts were made by software that can easily adjust to schedule changes. [1]
Chrome extension
Turn any webpage into a sticky note.
Stop losing tabs and copying links. One click saves the page, video or article you're looking at as a note on your wall. No typing, no forms, no copy-paste.
Add to Chrome, it's free →A worked example uses seven tasks, labeled a through g. Some tasks can be done concurrently, while others cannot begin until their predecessor task is complete. Each task has three time estimates: the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated using the beta probability distribution, with the formula (O + 4M + P) ÷ 6. [1]
Once this step is complete, a Gantt chart or a network diagram can be drawn. [1]
In a progress Gantt chart, tasks are shaded in proportion to the degree of their completion. A task that is 60% complete would be 60% shaded, starting from the left. A vertical line is drawn at the time index when the chart is created, and tasks can be compared with this line. If everything is on schedule, all task portions left of the line will be shaded. [1]
Linked Gantt charts contain lines indicating the dependencies between tasks. These charts quickly become cluttered in all but the simplest cases. Critical path network diagrams are considered superior for communicating relationships between tasks. Gantt charts are often preferred over network diagrams because they are easily interpreted without training, whereas critical path diagrams require training. [1]
The Gantt chart's widespread adoption is perhaps less based on its universal application and suitability than on the absence of any alternative. It flattens assumptions, which in turn can constrain the ability to respond to uncertainty and change. [1]