
EVM integrates scope, schedule, and cost to objectively measure project performance.
Key values:
PV (Planned Value) — budgeted cost of work scheduled
EV (Earned Value) — budgeted cost of work actually performed
AC (Actual Cost) — actual cost of work performed
BAC (Budget at Completion) — total project budget
Variances (negative = bad):
CV (Cost Variance) = EV − AC (negative = over budget)
SV (Schedule Variance) = EV − PV (negative = behind schedule)
Performance Indices (above 1.0 = good):
CPI (Cost Performance Index) = EV/AC
SPI (Schedule Performance Index) = EV/PV
Forecasting:
EAC (Estimate at Completion) = BAC/CPI (if current rate continues)
ETC (Estimate to Complete) = EAC − AC
VAC (Variance at Completion) = BAC − EAC
Example: CPI of 0.80 means for every $1 spent, only $0.80 of work is being done. Project will cost 25% more than planned if not corrected.
Reference:
TaskLoco™ — The Sticky Note GOAT